Dispute Resolution

Credible objective analysis and efficient settlement strategies

Clients choose CCi because of our industry and dispute resolution expertise.

Our delay, quantum and technical experts are specialists at resolving disputes. CCi’s incisive and objective analysis has resolved high-profile and complex global construction disputes. We are relentless in our pursuit of resolution before a case reaches arbitration, litigation or adjudication. Our strong track record of global dispute resolution shows the value of this focus.

Our consultants carry out detailed forensic analysis to establish the liabilities and entitlements of all parties to the dispute, prior to preparing a dispute resolution strategy that aligns to your business objectives, contract entitlements and costs of the process. Our aim is always to avoid formal proceedings by strategically negotiating a timely, cost-effective and amicable resolution.

Projects

CCi have worked on hundreds of projects worldwide. With specialist teams in time, cost and technical, across a broad range of industry experience, we bring clarity to the most complex of situations.

7.5 Hectare Central Business District Development

Location: Australia

CCi was appointed to quantify delay suffered to the construction of two commercial towers (43 and 39 floors respectively) in Sydney’s Central Business District (CBD) following a fire within the shared basement. Utilising a combination of windows analysis and collapsed as-built, CCi successfully identified productivity losses that were wholly unrelated to the fire and had overstated the fire’s critical path impact leading to a successful claim settlement.

High-Rise Construction

Location: USA

Two separate water intrusion events occurred during the construction of a high-rise residential building in New York City. The Insured submitted a delay claim for 13 months of delay to the completion date because of the first event. CCi was retained by underwriters to determine the delay caused by each event to the completion date. CCi’s analysis established that contract works, that had not been impacted by either of the Insured events, was causing critical delay to the completion date. Although each individual event had caused a delay, the critical delay was due to remaining contract works. As such, CCi established if the events had not occurred, the completion date would not have been improved from what was actually achieved.

Bridge Project

Location: USA

Construction of a bridge spanning the Ohio River was delayed as a result of flooding from a high river event. CCi was retained by underwriters to investigate the amount of delay caused to the project completion date by repairing damage from the flood. CCi’s analysis showed that while the flood had caused critical delay to the project completion date at the time of the loss, delays to procurement of sections of the bridge after the loss meant ultimately the flood caused no actual delay to the project completion date.