
187MW Hydro Power Plant
Location: Europe

Following the collapse of the project’s headrace tunnel, CCi was appointed as the delay expert to produce an analysis that would eventually facilitate a mediated settlement. CCi used a combination of a windows analysis and a modelled hypothetical critical path to identify the difference between the project’s actual duration and the project’s ‘but for’ duration, had the tunnel’s defects been rectified immediately prior to the collapse.