40Ha Container Terminal

Storm damage during the dredging and reclamation phase of the project resulted in the implementation of a suite of mitigation measures.
A primary critical path investigation was conducted to evaluate the ‘unmitigated’ impact of the damage to assist with the assessment of mitigation measures. Further detailed analysis of the contemporaneous project records was carried out to determine the eventual dominant cause of delay, identification of concurrent delay events, unrelated to the Damage event, and the date upon which the project would have commenced commercial operation had the storm damage not occurred. This analysis allowed for the successful negotiated settlement of the claim.

Australia

Airport Link Motorway

It was claimed that seven separate events had caused critical delay to the project’s completion date.

Europe

Subsea Production Umbilicals

Two damage events, both concerning cracking to the outer sheaths of the Umbilicals led to critical delay of the ‘load out’ milestone.

Chile

210MW Solar Plant

A fire occurred in the central tower of a solar plant where the solar receiver is located.

Australia

Vanadium Mine

Following fire damage at the world’s largest vanadium mine, two divergent hypothetical timelines emerged relating to the redesigned reinstatement of the beneficiation process plant.