40Ha Container Terminal

Storm damage during the dredging and reclamation phase of the project resulted in the implementation of a suite of mitigation measures.
A primary critical path investigation was conducted to evaluate the ‘unmitigated’ impact of the damage to assist with the assessment of mitigation measures. Further detailed analysis of the contemporaneous project records was carried out to determine the eventual dominant cause of delay, identification of concurrent delay events, unrelated to the Damage event, and the date upon which the project would have commenced commercial operation had the storm damage not occurred. This analysis allowed for the successful negotiated settlement of the claim.

Canada

Manufacturing / Heavy Industry

Following a large explosion and subsequent fire at a chemical manufacturing plant CCi was appointed by insurers to assess the duration of repairs required to restore the plant to its pre-loss production capacity.

North Sea

Semi-Submersible

A Semi-Submersible brown field project, consisting of the conversion of a large exploration vessel to a production vessel overran in time and in money.

Europe

187MW Hydro Power Plant

Following the collapse of the project’s headrace tunnel, CCi was appointed as the delay expert to produce an analysis that would eventually facilitate a mediated settlement.

India

Crude Oil Refinery

Unprecedented rainfall caused significant damage to stored equipment at the world’s largest refining hub, with crude processing capacity of 1.24 million barrels per day.