Subsea Production Umbilicals

Two damage events, both concerning cracking to the outer sheaths of the Umbilicals led to critical delay of the ‘load out’ milestone. CCi was appointed to assess the extent to which damage had delayed the project and to quantify associated liquidated damages. Utilising a time slice analysis, CCi’s analysis enabled a successful resolution of the claim.

UK

FPSO

CCi conducted a thorough timeline analysis of events surrounding catastrophic storm damage, during which four of the FPSO’s anchor chains snapped and the vessel drifted 180m off station.

UK

Roadway Project

CCi was appointed as expert to determine the time and quantum issues arising during construction.

USA

Bridge Project

Construction of a bridge spanning the Ohio River was delayed as a result of flooding from a high river event.

Australia

Floating Wet Concentrator Plant

The floating wet concentrator plant developed a sudden list (lean) to port side within the pond before settling on the bottom of the pond and mining was curtailed as a result.