Subsea Production Umbilicals

Two damage events, both concerning cracking to the outer sheaths of the Umbilicals led to critical delay of the ‘load out’ milestone. CCi was appointed to assess the extent to which damage had delayed the project and to quantify associated liquidated damages. Utilising a time slice analysis, CCi’s analysis enabled a successful resolution of the claim.

Australia

Vanadium Mine

Following fire damage at the world’s largest vanadium mine, two divergent hypothetical timelines emerged relating to the redesigned reinstatement of the beneficiation process plant.

UK

Combined Heat and Intelligent Power Plant (CHiP)

The Contractor entered into a D&B FIDIC form of contract and suffered over a year’s delay with the design, build and commissioning of the CHiP plant.

Auckland, New Zealand

Puhoi to Warkworth Motorway

CCi provided Independent delay expert service for the Contractor. The project was delivered through Public-Private Partnership between the New Zealand Government and the Northern Express Group (NX2) to design and construct a four-lane highway with a central median safety barrier.

Europe

187MW Hydro Power Plant

Following the collapse of the project’s headrace tunnel, CCi was appointed as the delay expert to produce an analysis that would eventually facilitate a mediated settlement.