Subsea Production Umbilicals

Two damage events, both concerning cracking to the outer sheaths of the Umbilicals led to critical delay of the ‘load out’ milestone. CCi was appointed to assess the extent to which damage had delayed the project and to quantify associated liquidated damages. Utilising a time slice analysis, CCi’s analysis enabled a successful resolution of the claim.

Colombia

2400MW Hydro Power Plant

Failure of the Auxiliary Diversion Tunnel (ADT) and subsequent flooding of the underground power complex caused severe delay to the completion of this project, resulting in fundamental changes in the design.

UK

714MW Offshore Wind Farm

Supply delays relating to some of the turbine jackets were alleged to have resulted in a critical delay to the project.

Australia

Vanadium Mine

Following fire damage at the world’s largest vanadium mine, two divergent hypothetical timelines emerged relating to the redesigned reinstatement of the beneficiation process plant.

Europe

Subsea Production Umbilicals

Two damage events, both concerning cracking to the outer sheaths of the Umbilicals led to critical delay of the ‘load out’ milestone.