Roadway Project

CCi was appointed as expert to determine the time and quantum issues arising during construction. CCi provided reports for adjudication and appeared at tribunal in arbitration to provide expert evidence which resulted in a successful project settlement.

Europe

Subsea Production Umbilicals

Two damage events, both concerning cracking to the outer sheaths of the Umbilicals led to critical delay of the ‘load out’ milestone.

USA

Potash Mine

A conveyor at a Potash mine that carried product to warehouses before it could be loaded onto trains and distributed to customers collapsed.

UK

Combined Heat and Intelligent Power Plant (CHiP)

The Contractor entered into a D&B FIDIC form of contract and suffered over a year’s delay with the design, build and commissioning of the CHiP plant.

Latin America

FPSO

Two FPSO’s were constructed at yards in Central America and fitted out in ports in Latin America.