210MW Solar Plant

A fire occurred in the central tower of a solar plant where the solar receiver is located. Carried out an investigation to establish the pre-incident position and performed a technical analysis of the critical route of the project and possible causes of any delay in commercial operation, which helped our client to facilitate early settlement.

Canada

Manufacturing / Heavy Industry

Following a large explosion and subsequent fire at a chemical manufacturing plant CCi was appointed by insurers to assess the duration of repairs required to restore the plant to its pre-loss production capacity.

Europe

Subsea Production Umbilicals

Two damage events, both concerning cracking to the outer sheaths of the Umbilicals led to critical delay of the ‘load out’ milestone.

USA

Bridge Project

Construction of a bridge spanning the Ohio River was delayed as a result of flooding from a high river event.

UK

275kV Infrastructure Project

CCi was appointed as the quantum expert on behalf of the contractor on a dispute between it and the conductor supplier involving an alleged defective conductor and the financial consequences of it.