Manufacturing / Heavy Industry

Following a large explosion and subsequent fire at a chemical manufacturing plant CCi was appointed by insurers to assess the duration of repairs required to restore the plant to its pre-loss production capacity. CCi’s analysis identified a number of additional construction activities in the rebuild timeline that were not required to repair the property to the condition it was in prior to the loss and amounted to an improved design of the plant.

UAE

Aluminium Smelter

Following force majeure events, the aluminium production facility suffered a total ‘freeze’ of all operating liquid aluminium pots.

Latin America

FPSO

Two FPSO’s were constructed at yards in Central America and fitted out in ports in Latin America.

UK

61MW Onshore Wind Farm

The Super Grid Transformer suffered delay during transit which led to critical delays to the phased handover of the plant.

Chile

210MW Solar Plant

A fire occurred in the central tower of a solar plant where the solar receiver is located.