Potash Mine

A conveyor at a Potash mine that carried product to warehouses before it could be loaded onto trains and distributed to customers collapsed. The collapse required the actual conveyor to be rebuilt and repairs to one of the warehouses where the conveyor had collapsed through the roof. Due to operational preference, the Insured decided to rebuild the conveyor in a different configuration than what was presented prior to the event. The new configuration required additional permitting from regulatory bodies that would not have been required if the conveyor was rebuilt in the same configuration as before the collapse. CCi was retained to determine for Insurers whether the delays caused by the requirement to re-permit increased the interruption period being claimed by the Insured.

Costa Rica

40Ha Container Terminal

Storm damage during the dredging and reclamation phase of the project resulted in the implementation of a suite of mitigation measures.

Norway

MOPUstor Platform

Defects identified during the grouting of the platform’s jack-up system were claimed to be the reason behind termination of the project’s construction contract.

Canada

Manufacturing / Heavy Industry

Following a large explosion and subsequent fire at a chemical manufacturing plant CCi was appointed by insurers to assess the duration of repairs required to restore the plant to its pre-loss production capacity.

Cairns, Australia

Bruce Highway – Cairns Southern Access Corridor – Stage 3

CCi was engaged by the consortium contractor to review the collaborative project agreement (Contract), recommend a mechanism for time extension under the Contract, and assess the Contractor’s submitted extension of time and associated costs claim.