Potash Mine

A conveyor at a Potash mine that carried product to warehouses before it could be loaded onto trains and distributed to customers collapsed. The collapse required the actual conveyor to be rebuilt and repairs to one of the warehouses where the conveyor had collapsed through the roof. Due to operational preference, the Insured decided to rebuild the conveyor in a different configuration than what was presented prior to the event. The new configuration required additional permitting from regulatory bodies that would not have been required if the conveyor was rebuilt in the same configuration as before the collapse. CCi was retained to determine for Insurers whether the delays caused by the requirement to re-permit increased the interruption period being claimed by the Insured.

UK

714MW Offshore Wind Farm

Supply delays relating to some of the turbine jackets were alleged to have resulted in a critical delay to the project.

Europe

187MW Hydro Power Plant

Following the collapse of the project’s headrace tunnel, CCi was appointed as the delay expert to produce an analysis that would eventually facilitate a mediated settlement.

UK

Combined Heat and Intelligent Power Plant (CHiP)

The Contractor entered into a D&B FIDIC form of contract and suffered over a year’s delay with the design, build and commissioning of the CHiP plant.

USA

Power Station

A significant fire damaged large sections of a partially constructed Power Plant. The Insured ultimately completed the project 18 months late and submitted a DSU claim for 18 months.