Power Station

A significant fire damaged large sections of a partially constructed Power Plant. The Insured ultimately completed the project 18 months late and submitted a DSU claim for 18 months. CCi analysed the project schedules and identified non-loss related delay occurring after the date of loss. CCi established that due to the non-loss related delay, but for the event, the project would have completed 12 months late. As such, the loss had only caused an additional 6 months of delay to the Commercial Operation Date.

USA

Steel Plant

The exhaust pipe from the top of a steel furnace collapsed through the roof and required repair before the furnace could return to production.

Canada

Oil & Gas

At the procurement stage of an Oil Sands Project, worked with the Owner’s Supply Chain and Legal departments over two years to prepare requests for proposal and draft, negotiate and resolve construction contracts.

USA

Bridge Project

Construction of a bridge spanning the Ohio River was delayed as a result of flooding from a high river event.

India

Crude Oil Refinery

Unprecedented rainfall caused significant damage to stored equipment at the world’s largest refining hub, with crude processing capacity of 1.24 million barrels per day.