Semi-Submersible

A Semi-Submersible brown field project, consisting of the conversion of a large exploration vessel to a production vessel overran in time and in money. As expected in the conversion of a 25 year old structure that has spent its life at sea, many variations and changes were required that had not been foreseen after the initial survey. Weather, changes and general delays led to a significant dispute. Appointed as experts in quantum the role was to present an independent report to the Tribunal. Once the expert report was produced the claimant conceded sufficient elements of their claim that a settlement for a third of the initial claim was agreed.

USA

1600MW Coal Fired Power Station

Following catastrophic failure of the ID fan, CCi was appointed to analyse the project’s rebuild schedule and to conduct a ‘health check’ assessing the schedule’s suitability with regards to supporting the overall project management process and assisting with the claim.

North Sea

Semi-Submersible

A Semi-Submersible brown field project, consisting of the conversion of a large exploration vessel to a production vessel overran in time and in money.

Europe

187MW Hydro Power Plant

Following the collapse of the project’s headrace tunnel, CCi was appointed as the delay expert to produce an analysis that would eventually facilitate a mediated settlement.

UK

Light Railway Project

CCi was appointed as quantum and delay experts to provide opinion on delays and extensions of time, together with the assessment of the Final Account.