Desalination Plant

Seven independent delay events were claimed to have impacted the critical path during the project to increase the desalination facilities’ annual output from 50 to 100 billion litres annually. Without formal delay preparation from the insured, CCi critically analysed the insured’s project schedules and contemporaneous progress records to independently verify the actual impact of the seven delay events over and above the delay that the project would have suffered without the seven incidents.

UK

Ground Engineering and Geotechnical Pre-construction Services Project (HS2)

CCi was appointed to provide claims management support on the largest geotechnical ground investigation programme in Europe, delivered from commencement to final account.

UK

Humber Pipeline Tunnel

The construction of a 5km National Grid replacement tunnel 30m below the Humber Estuary supplying a quarter of the UK’s national gas became the largest and longest hydraulically inserted gas pipeline and was the heaviest moving man-made object.

UK

Combined Heat and Intelligent Power Plant (CHiP)

The Contractor entered into a D&B FIDIC form of contract and suffered over a year’s delay with the design, build and commissioning of the CHiP plant.

Tamworth, Australia

Tamworth 330KV Capacitor Banks and SVC Works

CCi was engaged by the Subcontractor responsible for all civil and concrete works, to assess the contractual position in terms of extension of time entitlement and to produce a consolidated extension of time along with associated costs claim.