Desalination Plant

Seven independent delay events were claimed to have impacted the critical path during the project to increase the desalination facilities’ annual output from 50 to 100 billion litres annually. Without formal delay preparation from the insured, CCi critically analysed the insured’s project schedules and contemporaneous progress records to independently verify the actual impact of the seven delay events over and above the delay that the project would have suffered without the seven incidents.

Oman

International Airport

Post-tender advice to specialist contractor on FIDIC Yellow Book 1999 provisions as amended by particular conditions regarding schedule of prices, change and valuation of change prior to executing contracts.

Cairns, Australia

Bruce Highway – Cairns Southern Access Corridor – Stage 3

CCi was engaged by the consortium contractor to review the collaborative project agreement (Contract), recommend a mechanism for time extension under the Contract, and assess the Contractor’s submitted extension of time and associated costs claim.

Australia

Vanadium Mine

Following fire damage at the world’s largest vanadium mine, two divergent hypothetical timelines emerged relating to the redesigned reinstatement of the beneficiation process plant.

Saudi Arabia

Process Plant (acetic acid, CO & VAM)

Expert advisor – visiting the site in 2009/2010 and reviewing the Primavera critical path schedules to assess their reliability.