187MW Hydro Power Plant

Following the collapse of the project’s headrace tunnel, CCi was appointed as the delay expert to produce an analysis that would eventually facilitate a mediated settlement. CCi used a combination of a windows analysis and a modelled hypothetical critical path to identify the difference between the project’s actual duration and the project’s ‘but for’ duration, had the tunnel’s defects been rectified immediately prior to the collapse.

UK

61MW Onshore Wind Farm

The Super Grid Transformer suffered delay during transit which led to critical delays to the phased handover of the plant.

UK

Tunnel Drive Project

A tunnel drive of several kilometres with associated shafts and bore pits encountered unexpected physical conditions.

Europe

730MW Ultra-supercritical Coal Fired Power Station

Originally suffering a catastrophic failure of the transformer, the project suffered several delay events, including 13 instances of damage.

Colombia

2400MW Hydro Power Plant

Failure of the Auxiliary Diversion Tunnel (ADT) and subsequent flooding of the underground power complex caused severe delay to the completion of this project, resulting in fundamental changes in the design.