187MW Hydro Power Plant

Following the collapse of the project’s headrace tunnel, CCi was appointed as the delay expert to produce an analysis that would eventually facilitate a mediated settlement. CCi used a combination of a windows analysis and a modelled hypothetical critical path to identify the difference between the project’s actual duration and the project’s ‘but for’ duration, had the tunnel’s defects been rectified immediately prior to the collapse.

USA

Steel Plant

The exhaust pipe from the top of a steel furnace collapsed through the roof and required repair before the furnace could return to production.

North Sea

Semi-Submersible

A Semi-Submersible brown field project, consisting of the conversion of a large exploration vessel to a production vessel overran in time and in money.

Cairns, Australia

Bruce Highway – Cairns Southern Access Corridor – Stage 3

CCi was engaged by the consortium contractor to review the collaborative project agreement (Contract), recommend a mechanism for time extension under the Contract, and assess the Contractor’s submitted extension of time and associated costs claim.

UK

Combined Heat and Intelligent Power Plant (CHiP)

The Contractor entered into a D&B FIDIC form of contract and suffered over a year’s delay with the design, build and commissioning of the CHiP plant.