Crude Oil Refinery

Unprecedented rainfall caused significant damage to stored equipment at the world’s largest refining hub, with crude processing capacity of 1.24 million barrels per day. CCi was appointed to evaluate delays that occurred to the start-up of the J3 units affected by the flood. CCi identified the impact of manufacturing lead times of replacement equipment on the unit critical paths to notify insurers of their potential exposure.

Tamworth, Australia

Tamworth 330KV Capacitor Banks and SVC Works

CCi was engaged by the Subcontractor responsible for all civil and concrete works, to assess the contractual position in terms of extension of time entitlement and to produce a consolidated extension of time along with associated costs claim.

USA

Power Station

A significant fire damaged large sections of a partially constructed Power Plant. The Insured ultimately completed the project 18 months late and submitted a DSU claim for 18 months.

Chile

210MW Solar Plant

A fire occurred in the central tower of a solar plant where the solar receiver is located.

Canada

Manufacturing / Heavy Industry

Following a large explosion and subsequent fire at a chemical manufacturing plant CCi was appointed by insurers to assess the duration of repairs required to restore the plant to its pre-loss production capacity.