Crude Oil Refinery

Unprecedented rainfall caused significant damage to stored equipment at the world’s largest refining hub, with crude processing capacity of 1.24 million barrels per day. CCi was appointed to evaluate delays that occurred to the start-up of the J3 units affected by the flood. CCi identified the impact of manufacturing lead times of replacement equipment on the unit critical paths to notify insurers of their potential exposure.

UK

Humber Pipeline Tunnel

The construction of a 5km National Grid replacement tunnel 30m below the Humber Estuary supplying a quarter of the UK’s national gas became the largest and longest hydraulically inserted gas pipeline and was the heaviest moving man-made object.

Europe

Subsea Production Umbilicals

Two damage events, both concerning cracking to the outer sheaths of the Umbilicals led to critical delay of the ‘load out’ milestone.

USA

1600MW Coal Fired Power Station

Following catastrophic failure of the ID fan, CCi was appointed to analyse the project’s rebuild schedule and to conduct a ‘health check’ assessing the schedule’s suitability with regards to supporting the overall project management process and assisting with the claim.

Cairns, Australia

Bruce Highway – Cairns Southern Access Corridor – Stage 3

CCi was engaged by the consortium contractor to review the collaborative project agreement (Contract), recommend a mechanism for time extension under the Contract, and assess the Contractor’s submitted extension of time and associated costs claim.