1.4GW Combined Cycle Power Plant

During the equipment commissioning operation for the project’s steam turbine unit, a system error triggered an unscheduled shutdown of the lubricating oil pumps causing damage to the turbine shaft. The damage was such that the entire unit required replacement, although the Insured was able to carry out in-situ partial repairs to allow for temporary operation until the new unit could be procured. CCi was instructed to carry out a delay analysis on the project schedules to determine to what extent the incident delayed the Project Commercial Operation Date (COD). In carrying out the analysis, CCi used contemporaneous project records and construction schedules to identify several additional commissioning activities in the post-incident period that were not forecast at the time of the incident. CCi’s analysis of these activities is ongoing, focusing on whether the project would have experienced any delay to the forecast COD had the lube failure incident not occurred.

Cairns, Australia

Bruce Highway – Cairns Southern Access Corridor – Stage 3

CCi was engaged by the consortium contractor to review the collaborative project agreement (Contract), recommend a mechanism for time extension under the Contract, and assess the Contractor’s submitted extension of time and associated costs claim.

Australia

Desalination Plant

Seven independent delay events were claimed to have impacted the critical path during the project to increase the desalination facilities’ annual output from 50 to 100 billion litres annually.

Kazakhstan

Ferrochrome Smelter

A catastrophic breakout of molten metal caused significant damage to the construction of the ferrochrome melt shop.

UAE

Aluminium Smelter

Following force majeure events, the aluminium production facility suffered a total ‘freeze’ of all operating liquid aluminium pots.