Aluminium Smelter

Following force majeure events, the aluminium production facility suffered a total ‘freeze’ of all operating liquid aluminium pots. At the time of the incident the project was ramping up the newly constructed facilities. CCi’s role included preparation of a ‘but for’ assessment of the timeline-related factors. This identified events that would have interrupted the normal progress of the ramp-up process had the force majeure event not occurred.

USA

Steel Plant

The exhaust pipe from the top of a steel furnace collapsed through the roof and required repair before the furnace could return to production.

UK

Humber Pipeline Tunnel

The construction of a 5km National Grid replacement tunnel 30m below the Humber Estuary supplying a quarter of the UK’s national gas became the largest and longest hydraulically inserted gas pipeline and was the heaviest moving man-made object.

Australia

Desalination Plant

Seven independent delay events were claimed to have impacted the critical path during the project to increase the desalination facilities’ annual output from 50 to 100 billion litres annually.

UK

714MW Offshore Wind Farm

Supply delays relating to some of the turbine jackets were alleged to have resulted in a critical delay to the project.