Bruce Highway – Cairns Southern Access Corridor – Stage 3

CCi was engaged by the consortium contractor to review the collaborative project agreement (Contract), recommend a mechanism for time extension under the Contract, and assess the Contractor’s submitted extension of time and associated costs claim. The collaborative project agreement was a bespoke contract that is unique for the project and was not aligned with any of the common standard forms of contracts. CCi’s team developed a risk allocation matrix for the project and created flow charts for the contractual obligations in terms of extension of time notices and claims.

Auckland, New Zealand

Puhoi to Warkworth Motorway

CCi provided Independent delay expert service for the Contractor. The project was delivered through Public-Private Partnership between the New Zealand Government and the Northern Express Group (NX2) to design and construct a four-lane highway with a central median safety barrier.

Colombia

2400MW Hydro Power Plant

Failure of the Auxiliary Diversion Tunnel (ADT) and subsequent flooding of the underground power complex caused severe delay to the completion of this project, resulting in fundamental changes in the design.

UK

PFI Acute Emergency Hospital Project

CCi was appointed to compile numerous claim documents for MEP design fees arising from revisions to the architectural BIM model.

Canada

Oil & Gas

At the procurement stage of an Oil Sands Project, worked with the Owner’s Supply Chain and Legal departments over two years to prepare requests for proposal and draft, negotiate and resolve construction contracts.