Light Railway Project

CCi was appointed as quantum and delay experts to provide opinion on delays and extensions of time, together with the assessment of the Final Account. The team ensured that the delay and extension of time analysis was presented in a way that clearly showed the delays and entitlements to time and was also readily usable in quantum assessments. The matter was on track for litigation but was settled in subsequent mediation in which the experts played a prominent role.

USA

Potash Mine

A conveyor at a Potash mine that carried product to warehouses before it could be loaded onto trains and distributed to customers collapsed.

Saudi Arabia

Process Plant (acetic acid, CO & VAM)

Expert advisor – visiting the site in 2009/2010 and reviewing the Primavera critical path schedules to assess their reliability.

Europe

Double Deck Tunnel

A series of incidents concerning a Tunnel Boring Machine (TBM) with a diameter of 13.7m, were claimed to have caused delay to the critical path of the project.

Europe

730MW Ultra-supercritical Coal Fired Power Station

Originally suffering a catastrophic failure of the transformer, the project suffered several delay events, including 13 instances of damage.