Light Railway Project

CCi was appointed as quantum and delay experts to provide opinion on delays and extensions of time, together with the assessment of the Final Account. The team ensured that the delay and extension of time analysis was presented in a way that clearly showed the delays and entitlements to time and was also readily usable in quantum assessments. The matter was on track for litigation but was settled in subsequent mediation in which the experts played a prominent role.

Australia

Desalination Plant

Seven independent delay events were claimed to have impacted the critical path during the project to increase the desalination facilities’ annual output from 50 to 100 billion litres annually.

UK

Roadway Project

CCi was appointed as expert to determine the time and quantum issues arising during construction.

Europe

730MW Ultra-supercritical Coal Fired Power Station

Originally suffering a catastrophic failure of the transformer, the project suffered several delay events, including 13 instances of damage.

USA

Power Station

A significant fire damaged large sections of a partially constructed Power Plant. The Insured ultimately completed the project 18 months late and submitted a DSU claim for 18 months.