2400MW Hydro Power Plant

Failure of the Auxiliary Diversion Tunnel (ADT) and subsequent flooding of the underground power complex caused severe delay to the completion of this project, resulting in fundamental changes in the design. Detailed investigations were undertaken in accordance with the insurance policy exclusions to establish which delay events were attributable solely to the damage to the ADT or GAD as opposed to consequential delays caused by the defect improvement works or events unrelated to the incident. CCi’s analysis was relied upon to establish an agreement between the insured and insurers.

Tamworth, Australia

Tamworth 330KV Capacitor Banks and SVC Works

CCi was engaged by the Subcontractor responsible for all civil and concrete works, to assess the contractual position in terms of extension of time entitlement and to produce a consolidated extension of time along with associated costs claim.

UK

Combined Heat and Intelligent Power Plant (CHiP)

The Contractor entered into a D&B FIDIC form of contract and suffered over a year’s delay with the design, build and commissioning of the CHiP plant.

Oman

International Airport

Post-tender advice to specialist contractor on FIDIC Yellow Book 1999 provisions as amended by particular conditions regarding schedule of prices, change and valuation of change prior to executing contracts.

Brazil

1.4GW Combined Cycle Power Plant

During the equipment commissioning operation for the project’s steam turbine unit, a system error triggered an unscheduled shutdown of the lubricating oil pumps causing damage to the turbine shaft.