Humber Pipeline Tunnel

The construction of a 5km National Grid replacement tunnel 30m below the Humber Estuary supplying a quarter of the UK’s national gas became the largest and longest hydraulically inserted gas pipeline and was the heaviest moving man-made object. The JV Contractors suffered a year’s delay leading up to the launch of the Tunnel Boring Machine (TBM). CCi was engaged to forensically look at the reasons for the delays under the NEC3 form of contract. It resulted in the JV and National Grid negotiating a settlement as the works continued.

Oman

International Airport

Post-tender advice to specialist contractor on FIDIC Yellow Book 1999 provisions as amended by particular conditions regarding schedule of prices, change and valuation of change prior to executing contracts.

UK

Combined Heat and Intelligent Power Plant (CHiP)

The Contractor entered into a D&B FIDIC form of contract and suffered over a year’s delay with the design, build and commissioning of the CHiP plant.

Kazakhstan

Ferrochrome Smelter

A catastrophic breakout of molten metal caused significant damage to the construction of the ferrochrome melt shop.

Norway

MOPUstor Platform

Defects identified during the grouting of the platform’s jack-up system were claimed to be the reason behind termination of the project’s construction contract.