Humber Pipeline Tunnel

The construction of a 5km National Grid replacement tunnel 30m below the Humber Estuary supplying a quarter of the UK’s national gas became the largest and longest hydraulically inserted gas pipeline and was the heaviest moving man-made object. The JV Contractors suffered a year’s delay leading up to the launch of the Tunnel Boring Machine (TBM). CCi was engaged to forensically look at the reasons for the delays under the NEC3 form of contract. It resulted in the JV and National Grid negotiating a settlement as the works continued.

Cairns, Australia

Bruce Highway – Cairns Southern Access Corridor – Stage 3

CCi was engaged by the consortium contractor to review the collaborative project agreement (Contract), recommend a mechanism for time extension under the Contract, and assess the Contractor’s submitted extension of time and associated costs claim.

UK

Roadway Project

CCi was appointed as expert to determine the time and quantum issues arising during construction.

USA

Power Station

A significant fire damaged large sections of a partially constructed Power Plant. The Insured ultimately completed the project 18 months late and submitted a DSU claim for 18 months.

London

Shangri-La Hotel in The Shard

The prestigious fit out of the Shangri La hotel within the Shard tower had many employer design issues and a contractor defect issue which resulted in the termination of the contract.