Tamworth 330KV Capacitor Banks and SVC Works

CCi was engaged by the Subcontractor responsible for all civil and concrete works, to assess the contractual position in terms of extension of time entitlement and to produce a consolidated extension of time along with associated costs claim. CCi produced a compelling claim document that enabled the Subcontractor to recover over 80% of its claimed prolongation costs with an opportunity to negotiate the remainder. CCi’s experience was fundamental to the demonstration of the entitlement, production of the supporting evidence, and the negotiation of the settlement.

UK

Combined Heat and Intelligent Power Plant (CHiP)

The Contractor entered into a D&B FIDIC form of contract and suffered over a year’s delay with the design, build and commissioning of the CHiP plant.

Colombia

2400MW Hydro Power Plant

Failure of the Auxiliary Diversion Tunnel (ADT) and subsequent flooding of the underground power complex caused severe delay to the completion of this project, resulting in fundamental changes in the design.

Saudi Arabia

Process Plant (acetic acid, CO & VAM)

Expert advisor – visiting the site in 2009/2010 and reviewing the Primavera critical path schedules to assess their reliability.

USA

LNG Plant

A named windstorm caused widespread damage to the construction of an LNG plant.