Shangri-La Hotel in The Shard

The prestigious fit out of the Shangri La hotel within the Shard tower had many employer design issues and a contractor defect issue which resulted in the termination of the contract. CCi carried out a detailed time slice windows analysis to identify both the employer delay events and contractor performance and defect issues. Following a mediation, the employer started proceedings to the Technology & Construction Court, though within two months of the mediation the parties agreed a negotiated settlement.

Tamworth, Australia

Tamworth 330KV Capacitor Banks and SVC Works

CCi was engaged by the Subcontractor responsible for all civil and concrete works, to assess the contractual position in terms of extension of time entitlement and to produce a consolidated extension of time along with associated costs claim.

Costa Rica

40Ha Container Terminal

Storm damage during the dredging and reclamation phase of the project resulted in the implementation of a suite of mitigation measures.

USA

Potash Mine

A conveyor at a Potash mine that carried product to warehouses before it could be loaded onto trains and distributed to customers collapsed.

Oman

International Airport

Post-tender advice to specialist contractor on FIDIC Yellow Book 1999 provisions as amended by particular conditions regarding schedule of prices, change and valuation of change prior to executing contracts.