International Airport

Post-tender advice to specialist contractor on FIDIC Yellow Book 1999 provisions as amended by particular conditions regarding schedule of prices, change and valuation of change prior to executing contracts.

Australia

7.5 Hectare Central Business District Development

CCi was appointed to quantify delay suffered to the construction of two commercial towers (43 and 39 floors respectively) in Sydney’s Central Business District (CBD) following a fire within the shared basement.

USA

1600MW Coal Fired Power Station

Following catastrophic failure of the ID fan, CCi was appointed to analyse the project’s rebuild schedule and to conduct a ‘health check’ assessing the schedule’s suitability with regards to supporting the overall project management process and assisting with the claim.

UK

Ground Engineering and Geotechnical Pre-construction Services Project (HS2)

CCi was appointed to provide claims management support on the largest geotechnical ground investigation programme in Europe, delivered from commencement to final account.

Australia

Airport Link Motorway

It was claimed that seven separate events had caused critical delay to the project’s completion date.