714MW Offshore Wind Farm

Supply delays relating to some of the turbine jackets were alleged to have resulted in a critical delay to the project. CCi was appointed to determine the true criticality of the delay event. Using a combination of ‘but for’ and windows-based time slice analysis, CCi identified significant levels of float and flexibility within the project’s scheduled sequence, which could not be determined through the claimant’s preferred delay methodology, and ultimately led to agreement that no critical delay would likely be experienced and that no claim would be presented.

Europe

187MW Hydro Power Plant

Following the collapse of the project’s headrace tunnel, CCi was appointed as the delay expert to produce an analysis that would eventually facilitate a mediated settlement.

Europe

730MW Ultra-supercritical Coal Fired Power Station

Originally suffering a catastrophic failure of the transformer, the project suffered several delay events, including 13 instances of damage.

Saudi Arabia

Process Plant (acetic acid, CO & VAM)

Expert advisor – visiting the site in 2009/2010 and reviewing the Primavera critical path schedules to assess their reliability.

UK

FPSO

CCi conducted a thorough timeline analysis of events surrounding catastrophic storm damage, during which four of the FPSO’s anchor chains snapped and the vessel drifted 180m off station.