High-rise Construction

Two separate water intrusion events occurred during the construction of a high-rise residential building in New York City. The Insured submitted a delay claim for 13 months of delay to the completion date because of the first event. CCi was retained by underwriters to determine the delay caused by each event to the completion date. CCi’s analysis established that contract works, that had not been impacted by either of the Insured events, was causing critical delay to the completion date. Although each individual event had caused a delay, the critical delay was due to remaining contract works. As such, CCi established if the events had not occurred, the completion date would not have been improved from what was actually achieved.

Latin America

FPSO

Two FPSO’s were constructed at yards in Central America and fitted out in ports in Latin America.

Kazakhstan

Ferrochrome Smelter

A catastrophic breakout of molten metal caused significant damage to the construction of the ferrochrome melt shop.

UK

Light Railway Project

CCi was appointed as quantum and delay experts to provide opinion on delays and extensions of time, together with the assessment of the Final Account.

Colombia

2400MW Hydro Power Plant

Failure of the Auxiliary Diversion Tunnel (ADT) and subsequent flooding of the underground power complex caused severe delay to the completion of this project, resulting in fundamental changes in the design.