High-rise Construction

Two separate water intrusion events occurred during the construction of a high-rise residential building in New York City. The Insured submitted a delay claim for 13 months of delay to the completion date because of the first event. CCi was retained by underwriters to determine the delay caused by each event to the completion date. CCi’s analysis established that contract works, that had not been impacted by either of the Insured events, was causing critical delay to the completion date. Although each individual event had caused a delay, the critical delay was due to remaining contract works. As such, CCi established if the events had not occurred, the completion date would not have been improved from what was actually achieved.

India

Crude Oil Refinery

Unprecedented rainfall caused significant damage to stored equipment at the world’s largest refining hub, with crude processing capacity of 1.24 million barrels per day.

USA

Power Station

A significant fire damaged large sections of a partially constructed Power Plant. The Insured ultimately completed the project 18 months late and submitted a DSU claim for 18 months.

Chile

210MW Solar Plant

A fire occurred in the central tower of a solar plant where the solar receiver is located.

Canada

Manufacturing / Heavy Industry

Following a large explosion and subsequent fire at a chemical manufacturing plant CCi was appointed by insurers to assess the duration of repairs required to restore the plant to its pre-loss production capacity.