LNG Plant

A named windstorm caused widespread damage to the construction of an LNG plant. Significant damage was caused to pipe that had been prefabricated and was waiting to be installed at the facility. CCi carried out an analysis of the delays incurred to the project prior to the storm and identified pre-storm delay that had not been accounted for in the forecast Commercial Operation Date (COD). In addition, CCi identified delays to the fabrication and installation of structural steel that meant the delay caused to the COD by having to replace pipe was much less than originally claimed by the Insured.

Costa Rica

40Ha Container Terminal

Storm damage during the dredging and reclamation phase of the project resulted in the implementation of a suite of mitigation measures.

Norway

MOPUstor Platform

Defects identified during the grouting of the platform’s jack-up system were claimed to be the reason behind termination of the project’s construction contract.

USA

1600MW Coal Fired Power Station

Following catastrophic failure of the ID fan, CCi was appointed to analyse the project’s rebuild schedule and to conduct a ‘health check’ assessing the schedule’s suitability with regards to supporting the overall project management process and assisting with the claim.

USA

Potash Mine

A conveyor at a Potash mine that carried product to warehouses before it could be loaded onto trains and distributed to customers collapsed.