Crude Oil Refinery

Unprecedented rainfall caused significant damage to stored equipment at the world’s largest refining hub, with crude processing capacity of 1.24 million barrels per day. CCi was appointed to evaluate delays that occurred to the start-up of the J3 units affected by the flood. CCi identified the impact of manufacturing lead times of replacement equipment on the unit critical paths to notify insurers of their potential exposure.

Kazakhstan

Ferrochrome Smelter

A catastrophic breakout of molten metal caused significant damage to the construction of the ferrochrome melt shop.

Canada

Manufacturing / Heavy Industry

Following a large explosion and subsequent fire at a chemical manufacturing plant CCi was appointed by insurers to assess the duration of repairs required to restore the plant to its pre-loss production capacity.

Thailand

Underground Potash Mine

During commissioning of the mine, an underground inrush flooded the mine causing damage.

UK

London Underground Line Extension Project (Crossrail)

CCI was appointed to provide commercial support and key performance and cost indicators to the executive board.