At the procurement stage of an Oil Sands Project, worked with the Owner’s Supply Chain and Legal departments over two years to prepare requests for proposal and draft, negotiate and resolve construction contracts.

USA

Power Station

A significant fire damaged large sections of a partially constructed Power Plant. The Insured ultimately completed the project 18 months late and submitted a DSU claim for 18 months.

Kazakhstan

Ferrochrome Smelter

A catastrophic breakout of molten metal caused significant damage to the construction of the ferrochrome melt shop.

North Sea

Semi-Submersible

A Semi-Submersible brown field project, consisting of the conversion of a large exploration vessel to a production vessel overran in time and in money.

Norway

MOPUstor Platform

Defects identified during the grouting of the platform’s jack-up system were claimed to be the reason behind termination of the project’s construction contract.