7.5 Hectare Central Business District Development

CCi was appointed to quantify delay suffered to the construction of two commercial towers (43 and 39 floors respectively) in Sydney’s Central Business District (CBD) following a fire within the shared basement. Utilising a combination of windows analysis and collapsed as-built, CCi successfully identified productivity losses that were wholly unrelated to the fire and had overstated the fire’s critical path impact leading to a successful claim settlement.

Cairns, Australia

Bruce Highway – Cairns Southern Access Corridor – Stage 3

CCi was engaged by the consortium contractor to review the collaborative project agreement (Contract), recommend a mechanism for time extension under the Contract, and assess the Contractor’s submitted extension of time and associated costs claim.

Brazil

1.4GW Combined Cycle Power Plant

During the equipment commissioning operation for the project’s steam turbine unit, a system error triggered an unscheduled shutdown of the lubricating oil pumps causing damage to the turbine shaft.

USA

Bridge Project

Construction of a bridge spanning the Ohio River was delayed as a result of flooding from a high river event.

India

Crude Oil Refinery

Unprecedented rainfall caused significant damage to stored equipment at the world’s largest refining hub, with crude processing capacity of 1.24 million barrels per day.