7.5 Hectare Central Business District Development

CCi was appointed to quantify delay suffered to the construction of two commercial towers (43 and 39 floors respectively) in Sydney’s Central Business District (CBD) following a fire within the shared basement. Utilising a combination of windows analysis and collapsed as-built, CCi successfully identified productivity losses that were wholly unrelated to the fire and had overstated the fire’s critical path impact leading to a successful claim settlement.

Norway

MOPUstor Platform

Defects identified during the grouting of the platform’s jack-up system were claimed to be the reason behind termination of the project’s construction contract.

Oman

International Airport

Post-tender advice to specialist contractor on FIDIC Yellow Book 1999 provisions as amended by particular conditions regarding schedule of prices, change and valuation of change prior to executing contracts.

Thailand

Underground Potash Mine

During commissioning of the mine, an underground inrush flooded the mine causing damage.

Canada

Manufacturing / Heavy Industry

Following a large explosion and subsequent fire at a chemical manufacturing plant CCi was appointed by insurers to assess the duration of repairs required to restore the plant to its pre-loss production capacity.