Steel Plant

The exhaust pipe from the top of a steel furnace collapsed through the roof and required repair before the furnace could return to production. During the demolition of the damaged structure, the crane removing debris overturned and caused additional damage and delay. CCi was appointed by Insurer’s to analyse the repair timeline and determine whether the second event had caused an increase to the interruption period of the furnace. CCi established the date the repairs should have completed if the second event had not occurred, and the additional delay caused by repairing damage from the second event.

USA

Potash Mine

A conveyor at a Potash mine that carried product to warehouses before it could be loaded onto trains and distributed to customers collapsed.

UK

Combined Heat and Intelligent Power Plant (CHiP)

The Contractor entered into a D&B FIDIC form of contract and suffered over a year’s delay with the design, build and commissioning of the CHiP plant.

UK

Roadway Project

CCi was appointed as expert to determine the time and quantum issues arising during construction.

UK

714MW Offshore Wind Farm

Supply delays relating to some of the turbine jackets were alleged to have resulted in a critical delay to the project.