Combined Heat and Intelligent Power Plant (CHiP)

The Contractor entered into a D&B FIDIC form of contract and suffered over a year’s delay with the design, build and commissioning of the CHiP plant. CCi carried out an in-depth analysis tracing the design delays in respect of the employers operating philosophy of the plant, which linked to the delays suffered in construction and later the commissioning issues. CCi identified significant culpability and concurrency issues and, following advice, the two parties eventually settled.

Canada

Manufacturing / Heavy Industry

Following a large explosion and subsequent fire at a chemical manufacturing plant CCi was appointed by insurers to assess the duration of repairs required to restore the plant to its pre-loss production capacity.

UK

714MW Offshore Wind Farm

Supply delays relating to some of the turbine jackets were alleged to have resulted in a critical delay to the project.

Brazil

1.4GW Combined Cycle Power Plant

During the equipment commissioning operation for the project’s steam turbine unit, a system error triggered an unscheduled shutdown of the lubricating oil pumps causing damage to the turbine shaft.

UK

Tunnel Drive Project

A tunnel drive of several kilometres with associated shafts and bore pits encountered unexpected physical conditions.