Ferrochrome Smelter

A catastrophic breakout of molten metal caused significant damage to the construction of the ferrochrome melt shop. CCi was appointed as delay expert to objectively separate critical delay from the breakout and delays resultant from ongoing procurement issues for key equipment located elsewhere in the project. CCi conducted a ‘but for’ assessment of the project status based on contemporaneous information and a detailed review of ‘pacing’. Both assessments contributed to a successful claim settlement.

USA

Bridge Project

Construction of a bridge spanning the Ohio River was delayed as a result of flooding from a high river event.

Brazil

1.4GW Combined Cycle Power Plant

During the equipment commissioning operation for the project’s steam turbine unit, a system error triggered an unscheduled shutdown of the lubricating oil pumps causing damage to the turbine shaft.

Kazakhstan

Ferrochrome Smelter

A catastrophic breakout of molten metal caused significant damage to the construction of the ferrochrome melt shop.

Europe

187MW Hydro Power Plant

Following the collapse of the project’s headrace tunnel, CCi was appointed as the delay expert to produce an analysis that would eventually facilitate a mediated settlement.