1.4GW Combined Cycle Power Plant

During the equipment commissioning operation for the project’s steam turbine unit, a system error triggered an unscheduled shutdown of the lubricating oil pumps causing damage to the turbine shaft. The damage was such that the entire unit required replacement, although the Insured was able to carry out in-situ partial repairs to allow for temporary operation until the new unit could be procured. CCi was instructed to carry out a delay analysis on the project schedules to determine to what extent the incident delayed the Project Commercial Operation Date (COD). In carrying out the analysis, CCi used contemporaneous project records and construction schedules to identify several additional commissioning activities in the post-incident period that were not forecast at the time of the incident. CCi’s analysis of these activities is ongoing, focusing on whether the project would have experienced any delay to the forecast COD had the lube failure incident not occurred.

USA

Power Station

A significant fire damaged large sections of a partially constructed Power Plant. The Insured ultimately completed the project 18 months late and submitted a DSU claim for 18 months.

UK

Combined Heat and Intelligent Power Plant (CHiP)

The Contractor entered into a D&B FIDIC form of contract and suffered over a year’s delay with the design, build and commissioning of the CHiP plant.

Colombia

2400MW Hydro Power Plant

Failure of the Auxiliary Diversion Tunnel (ADT) and subsequent flooding of the underground power complex caused severe delay to the completion of this project, resulting in fundamental changes in the design.

UK

714MW Offshore Wind Farm

Supply delays relating to some of the turbine jackets were alleged to have resulted in a critical delay to the project.