Projects

Brazil

1.4GW Combined Cycle Power Plant

During the equipment commissioning operation for the project’s steam turbine unit, a system error triggered an unscheduled shutdown of the lubricating oil pumps causing damage to the turbine shaft.

Chile

210MW Solar Plant

A fire occurred in the central tower of a solar plant where the solar receiver is located.

Colombia

2400MW Hydro Power Plant

Failure of the Auxiliary Diversion Tunnel (ADT) and subsequent flooding of the underground power complex caused severe delay to the completion of this project, resulting in fundamental changes in the design.

Costa Rica

40Ha Container Terminal

Storm damage during the dredging and reclamation phase of the project resulted in the implementation of a suite of mitigation measures.

Auckland, New Zealand

Puhoi to Warkworth Motorway

CCi provided Independent delay expert service for the Contractor. The project was delivered through Public-Private Partnership between the New Zealand Government and the Northern Express Group (NX2) to design and construct a four-lane highway with a central median safety barrier.

Cairns, Australia

Bruce Highway – Cairns Southern Access Corridor – Stage 3

CCi was engaged by the consortium contractor to review the collaborative project agreement (Contract), recommend a mechanism for time extension under the Contract, and assess the Contractor’s submitted extension of time and associated costs claim.

Tamworth, Australia

Tamworth 330KV Capacitor Banks and SVC Works

CCi was engaged by the Subcontractor responsible for all civil and concrete works, to assess the contractual position in terms of extension of time entitlement and to produce a consolidated extension of time along with associated costs claim.

North Sea

Semi-Submersible

A Semi-Submersible brown field project, consisting of the conversion of a large exploration vessel to a production vessel overran in time and in money.

Latin America

FPSO

Two FPSO’s were constructed at yards in Central America and fitted out in ports in Latin America.

Canada

Manufacturing / Heavy Industry

Following a large explosion and subsequent fire at a chemical manufacturing plant CCi was appointed by insurers to assess the duration of repairs required to restore the plant to its pre-loss production capacity.

Canada

Oil & Gas

At the procurement stage of an Oil Sands Project, worked with the Owner’s Supply Chain and Legal departments over two years to prepare requests for proposal and draft, negotiate and resolve construction contracts.

Saudi Arabia

Process Plant (acetic acid, CO & VAM)

Expert advisor – visiting the site in 2009/2010 and reviewing the Primavera critical path schedules to assess their reliability.